The Tri Viet 1 Solar Power Plant project, with a capacity of 30MWp, is invested by Tri Viet Tay Ninh Joint Stock Company. Located in the semi-submerged area of Dau Tieng Lake in Hamlet 5, Suoi Day Commune, Tan Chau District, Tay Ninh Province, it commenced commercial operation on May 28, 2019.
The Tri Viet 1 Solar Power Plant includes: 90,900 polycrystalline photovoltaic panels from CanadianSolar with a capacity of 330Wp. It also features an 8 SUNGROW DC/AC inverter system using Central Inverter technology. The 22/110kV substation uses a TAIKAI transformer with a capacity of 40MVA.
The PESE O&M team took over operation and maintenance from May 15, 2024, ensuring continuous and stable plant operation in compliance with state regulations and procedures. POM ensures the plant's availability factor (AF) is above 99%.